ANALISIS FAKTOR-FAKTOR KETERLAMBATAN PADA PROYEK PEMBANGUNAN EXPAND & ENHANCEMENT NEUCENTRIX PUGERAN YOGYAKARTA MENGGUNAKAN SPSS

Putri Pinuji, Putri Anggi Permata Suwandi, Mohammad Debby Rizani

Abstract


The 2023 Neucentrix Expand & Enhancement Development Project Pugeran Yogyakarta is planned to last 19 weeks. However, there was a delay due to the large amount of additional work and new items that were not listed in the BoQ. This research aims to identify the main factors causing project delays. The data used came from a questionnaire and then factor analysis was carried out using SPSS. A total of 11 managerial team respondents filled out the questionnaire, producing 18 valid variables that were very reliable. The results of the analysis show 5 rankings of the main factors causing delays, namely: delayed payments have an impact on project delays; changes in costs due to additional work; less than optimal labor productivity; error in basic price estimation in the Cost Budget Plan; difficulty in finding materials and/or equipment due to certain specialties; submission and request for changes to completed work from the project owner; changes in work methods by contractors; lack of adequate workforce; owner's delay in making decisions; changes to the scope of work (SOW) during implementation; and lack of workforce discipline regarding attendance and attendance, which hampers work time

Keywords


delay; time; analysis factors; SPSS

Full Text:

PDF

References


Amin, N. F., Garancang, S., & Abunawas, K. (2023). “Konsep Umum Populasi dan Sampel dalam Penelitian”. PILAR, 14(1), 15-31.

Hassan, H., Mangare, J. B., & Pratasis, P. A. K. (2016). “Faktor-Faktor Penyebab Keterlambatan pada Proyek Konstruksi dan Alternatif Penyelesaiannya (Studi Kasus: di Manado TownSquare III)”. Jurnal Sipil Statik, 4(11), 657–664.

Indrawan Sanny, B., Kaniawati Dewi, R., & oleh Politeknik Dharma Patria Kebumen, D. (2020). “Pengaruh Net Interest Margin (NIM) Terhadap Return on Asset (ROA) Pada PT Bank Pembangunan Daerah Jawa Barat Dan Banten Tbk Periode 2013-2017”. Jurnal E-Bis (Ekonomi-Bisnis) 4(1), 78–87.

Khoirul, K., Pristianto, H., & Rusmin, M. (2017). “Analisis Penyebab Keterlambatan Pekerjaan Konstruksi Jembatan”. Jurnal Teknik Sipil Rancang Bangun, 2(2), 27-36.

Janna, N., & Pembimbing, D. (2021). “Konsep Uji Validitas dan Reliabilitas dengan Menggunakan SPSS”.

Sanaky, M. M. (2021). “Analisis Faktor-Faktor Keterlambatan Pada Proyek Pembangunan Gedung Asrama Man 1 Tulehu Maluku Tengah”. Jurnal Simetrik, 11(1), 432-439.

Studi, P., Sipil, T., Boy, W., Erlindo, R., Ridho, D., & Fitrah, A. (2021). “Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Gedung Kuliah pada Masa Pandemi Covid 19”. Jurnal RIVET (Riset dan Invensi Teknologi) In Universitas Dharma Andalas (Vol. 01, Issue 1).




DOI: https://doi.org/10.26877/giratory.v6i1.24096

Refbacks

  • There are currently no refbacks.


Creative Commons License
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

Jurnal Teknik Sipil Giratory UPGRIS

Program Studi Teknik Sipil

Fakultas Teknik dan Informatika

Universitas PGRI Semarang